Since July, the crossing at Longs Peak Avenue and Atwood Street has had a four-quadrant gate: two arms on each side of the tracks, so every lane is blocked when a train comes through. Trains still sound their horns there, just as they did before the work started. The same goes for 3rd Avenue, 9th Avenue and 17th Avenue, the other three crossings the City finished in its first round of construction.
The BNSF line carries up to 17 trains a day through Longmont, and federal rules require a horn at every public crossing. The City's current schedule shows how the quiet will spread. The crossings at 5th Avenue/Atwood Street and Terry Street/1st Avenue are expected to go quiet in early 2027, alongside 17th Avenue, and they are the two being closed for good. The gates already built near them sit and wait for their neighbors.
Finished gates still need a federal sign-off
Building the safety upgrades is one step. Turning off the horns is another, and it isn't up to the City. Once a group of crossings is done, Longmont files a request with the Federal Railroad Administration, and the quiet zone starts only if the FRA approves it. For the first group, the City's project page says that request will be filed in summer 2027, a year after the concrete set.
Location matters just as much. The City's 2025–29 capital plan calls the 3rd, 4th, 5th, 6th and Longs Peak crossings a closely spaced group in the Historic East Side. When crossings sit a few blocks apart, a horn at one is heard at all of them. The City's quiet zone FAQ gives the local example:
"Since many of the crossings are clustered together, you may continue to hear train horns from other nearby crossings even after one is completed. For example, when the Longs Peak Avenue crossing is complete, you may continue to hear train horns at 6th Avenue until that crossing is complete."
So the Longs Peak gate is ready, but the East Side won't get quieter until 4th and 6th Avenues catch up. Both are under construction this fall.
Closing a crossing is the quickest path to quiet
A train has no reason to sound a horn at a crossing that no longer exists. On the City's citywide page, 5th Avenue/Atwood and Terry Street are listed for early 2027, ahead of the gated East Side crossings, and both entries are marked "crossing closure." The City says it chose those two for permanent closure based on traffic volume, how close they are to other crossings, and how practical other safety measures would be.
Terry Street has already closed. In mid-October, crews built a new access road from the north end of Terry Street to Coffman Street, and then the railroad crossing closed permanently to vehicles and pedestrians. Businesses north of the tracks are now reached from Coffman, between 1st and 2nd Avenues. Downtown Longmont's business directory lists Historic Callahan House and Garden at 312 Terry St and St. Vrain Cidery at 350 Terry St.
5th Avenue is next. When construction starts there, which the City expects in early December, the crossing will close permanently to cars, bikes and pedestrians, with no through traffic on 5th Avenue across the tracks. East-west trips will use 4th or 6th Avenue instead. For anyone who walks or bikes to NewCastle Comics at 508 5th Ave, the route over the tracks will move a block in either direction.
5th Avenue also has one last job. It stays open until 4th and 6th are finished, and while those two are fully closed it carries the detour traffic.
Five weeks of crossing changes, in order
As of the City's October 28 update, these are the dates to plan around. Every date is an estimate that can move with weather, railroad coordination or site conditions.
- Terry Street at 1st Avenue, closed for good since mid-October. Pedestrians traveling east and west should use the S. Pratt Parkway sidewalk to Boston Avenue, because 1st Avenue has no pedestrian access between the S. Pratt Parkway bridge and Main Street.
- 21st Avenue, closed now through about November 18. Drivers detour via Collyer Street, 17th Avenue and Alpine Street. The entrance to the Villas at Park Crest has no outlet, so the City asks drivers to stay on the marked detour and not cut through the complex. On foot or bike, cross to the south side of 21st Avenue and use the crosswalks there.
- 4th and 6th Avenues at Atwood, intermittent lane closures through mid-November. Flaggers direct traffic at the crossing during the closures. Atwood is one-way on both sides of the tracks from 3rd Avenue to Longs Peak Avenue. Pedestrians can't cross the tracks at 4th or 6th right now and should use 3rd, 5th or Longs Peak.
- 4th and 6th Avenues at Atwood, full closure starting around November 17 for about a week. Traffic detours via 5th Avenue and Longs Peak Avenue.
- 5th Avenue at Atwood, permanent closure starting early December.
Crews work Monday through Friday from 7 a.m. to 5 p.m. Some work may run until 7 p.m. or happen on weekends, and trains keep running the whole time.
When the horns are expected to stop, crossing by crossing
The project upgrades 14 crossings in four construction groups, and each group goes out to bid separately. The City says the phasing spreads out the disruption and leaves time for the FRA approvals. The schedule below is the City's current estimate.
| Crossing | Construction | Routine horns expected to stop |
|---|---|---|
| 17th Avenue | Finished July 2026 | Early 2027 |
| 5th Avenue/Atwood | Permanent closure begins early December 2026 | Early 2027 |
| Terry Street/1st Avenue | Permanently closed October 2026 | Early 2027 |
| 3rd Avenue/Atwood, Longs Peak Avenue, 9th Avenue | Finished July 2026 | Summer 2027 |
| 4th Avenue/Atwood, 6th Avenue/Atwood, 21st Avenue | Late summer 2026 to early 2027 | Summer 2027 |
| Main Street, Coffman Street, Mountain View Avenue | Spring 2027 to fall 2027 | Spring 2028 |
| State Highway 66, Hover Street | Summer 2027 to winter 2027 | Summer 2028 |
The crossings get different equipment. 3rd Avenue, Longs Peak, 4th and 6th get four-quadrant gates. 9th, 17th and 21st get two-quadrant gates with a raised median that keeps drivers from swinging around a lowered arm. According to the City, four-quadrant gates have been shown to cut collisions at grade crossings by up to 98 percent.
Three crossings aren't part of the grant work. The City is improving them separately with money from its voter-approved ¾-cent Street Fund sales and use tax, and the Emery Street crossing is already finished. The other 14 are partly funded by a $4 million FRA grant. The Longmont Times-Call reported when that award was announced in 2020.
1st Avenue waits until 2028, and gets rebuilt in the meantime
In the table, the 1st Avenue corridor sits near the bottom. Main Street and Coffman Street are in Group 3, with horns expected to stop in spring 2028. That stretch is busy. Downtown Longmont's directory lists 300 Suns Brewing, The Canvas Local Art Bar and The Tilted Brick at 333 and 335 1st Ave.
The same blocks are also being remade by a separate project. Ground broke on October 9 for the 1st & Main Transit Station, a $70 million station and Coffman Street project with 10 bus bays, about 700 parking spaces and bike storage, and the Times-Call reported a target finish by the end of 2027. The City's schedule then has commercial and apartment construction around the station from early 2027 through the end of 2028, with about 250 homes planned. Crews are now removing petroleum-impacted soil left by a former gas station on the site. The City says gasoline-like odors may come up during digging and does not expect public health impacts.
So the area around Terry Street gets a closed crossing now, a new garage and bus station by late 2027, and quiet at Main and Coffman around spring 2028.
What a quiet zone still sounds like
Even after the FRA signs off, a quiet zone won't be silent. Engineers can still sound the horn for hazards on the tracks, like people or animals. The bells on the gate poles keep ringing as a warning for pedestrians and cyclists. In practice, a block that hears a long horn blast at every train today will hear the bell at its own crossing. Sometime in 2027 or 2028, depending on which crossing is closest, the up to 17 trains a day will pass without the horn.
For questions about construction or the schedule, the City's quiet zone line is 720-526-2044, or email [email protected].